| 10399 |
Bhs Athletic Field |
3j Consulting *Brian O'Rourke* |
Resubmittal Required |
6/5/2026 |
1 |
| 10362 |
Kensington Square Subdivision |
7 Oaks Engineering *Steven Johnson* |
Resubmittal Required |
4/14/2026 |
2 |
| 10400 |
Amaterra Winery Addition |
Dowl *Drew Rommel* |
Resubmittal Required |
6/3/2026 |
1 |
| 10401 |
Amaterra Guest Suites |
Dowl *Drew Rommel* |
Initial Review on/before 07/02/2026 |
6/11/2026 |
1 |
| 10259 |
Farmington 5 Lot Subdivision |
Emerio Design *Pam Boyd* |
Resubmittal Required |
3/23/2026 |
2 |
| 10384 |
Sunset Hills Park Expansion Phase 1 |
Firwood Design Group *Kelli Grover* |
Resubmittal Review on/before 06/24/2026 |
6/10/2026 |
3 |
| 10337 |
Taylors Ferry - 2 Lot Parcel |
Fosse Engineering Llc *Brian Fosse* |
Resubmittal Required |
4/13/2026 |
2 |
| 10383 |
Saqsaqa Park - Thprd |
Froelich Engineers, Inc *Ben Ullman* |
Resubmittal Review on/before 06/24/2026 |
6/10/2026 |
3 |
| 10394 |
Meadow School Updates - Canceled |
Harper Houf Peterson Reghellis Inc *Bobby Jacobson* |
Canceled |
4/22/2026 |
|
| 10403 |
Wc - 26-27 Ada Ramps #4 |
Johnson, Johnny *Johnny Johnson* |
Initial Review on/before 07/03/2026 |
6/12/2026 |
1 |
| 10393 |
Nyg Connector |
Kimley-Horn *Tyler Ott* |
Issued |
6/8/2026 |
|
| 10382 |
West Union Chevron |
Kpff Consulting Engineers *Eric Melle* |
Resubmittal Required |
5/27/2026 |
2 |
| 10398 |
Kensington - Ec Only - Canceled |
7 Oaks Engineering *Steven Johnson* |
Canceled |
5/20/2026 |
|
| 10380 |
East River Fellowship Addition |
Mai Civil Engineering, Llc *Thu Mai* |
Resubmittal Required |
6/18/2026 |
3 |
| 10333 |
The Garage Food Cart |
Nw Engineers *Brad Nelson* |
Resubmittal Review on/before 06/17/2026 |
6/3/2026 |
3 |
| 10343 |
Leahy Subdivision |
Nw Engineers *Brad Nelson* |
Resubmittal Review on/before 06/24/2026 |
6/10/2026 |
3 |
| 10387 |
Islamic Community Cultural Center |
Nw Engineers *Brad Nelson* |
Resubmittal Required |
5/22/2026 |
1 |
| 10327 |
Deloris Middle Housing - Canceled |
Nw Engineers *Steve White* |
Canceled |
6/16/2026 |
|
| 10356 |
Yang Subdivision |
Nw Engineers *Steve White* |
Resubmittal Required |
9/24/2025 |
1 |
| 10375 |
Sunset View At West Banks - Phase 2 & 3 |
Pacific Community Design *Jaki Hunt* |
Early EC Review - Info Requested |
6/9/2026 |
0 |
| 10375 |
Sunset View At West Banks - Phase 2 & 3 |
Pacific Community Design *Jaki Hunt* |
Resubmittal Review on/before 06/22/2026 |
6/5/2026 |
4 |
| 10371 |
Goodrich Gardens |
Pioneer Design Group *William Doster* |
Approved |
6/5/2026 |
|
| 10183 |
Estates At Leahy Park |
Pioneer Design Group, Inc *Luke Lappin* |
Resubmittal Review on/before 06/23/2026 |
6/3/2026 |
8 |
| 10392 |
Aerts Addition Phase 2 |
Aks Engineering & Forestry, Llc *Chris Hockert* |
Early EC Review on/before 06/24/2026 |
6/2/2026 |
N/A |
| 10378 |
Cornell Road Middle Housing |
Pioneer Design Group, Inc *Luke Lappin* |
Resubmittal Required |
2/3/2026 |
1 |
| 10388 |
Cls - Mhlp - Addition |
Rsg Engineering *Richard Georgescu* |
Approved |
4/23/2026 |
|
| 10395 |
One Oak Mh |
Stantec *Chris Kittredge* |
Resubmittal Required |
5/14/2026 |
1 |
| 10397 |
Dez Cottage Cluster |
Summit Engineering Llc *Jason Havelka* |
Resubmittal Required |
5/19/2026 |
1 |
| 10340 |
Briggs Common Townhomes |
Tibbot Engineering Llc *Paul Tibbot* |
Resubmittal Required |
10/7/2025 |
1 |
| 10345 |
Panda Express Hillsboro |
Wallace Design Collective *Mary Clare Amer* |
Approved |
6/8/2026 |
|
| 10385 |
Haven Center |
Wcl Engineering Llc *William Lanthrop* |
Resubmittal Required |
4/15/2026 |
1 |
| 10381 |
White Pine - 2 Parcel Partition |
Wdy *Kari Kuboyama* |
Approved |
6/15/2026 |
|
| 10404 |
Raleigh Hills Townhomes |
Wdy *Kari Kuboyama* |
Insert Fee for Plan Check App |
6/18/2026 |
0 |
| 10391 |
Finley Sunset Ma Bldg |
Wdy Inc. *Scott Walker* |
Resubmittal Review on/before 06/23/2026 |
6/9/2026 |
2 |
| 10392 |
Aerts Addition Phase 2 |
Aks Engineering & Forestry, Llc *Chris Hockert* |
Resubmittal Required |
5/12/2026 |
1 |
| 10304 |
Creekside At Westview Phase 3 |
Westlake Consultants *Jacob Bibb* |
Issued |
5/12/2026 |
|
| 10014 |
Cornell Gardens |
Ztec Engineers *John Middleton* |
Resubmittal Required |
11/18/2025 |
6 |
| 10402 |
Aerts City Park |
Aks Engineering & Forestry, Llc *Chris Hockert* |
Initial Review on/before 06/22/2026 |
6/5/2026 |
1 |
| 10390 |
Westview Hs Turf Conversion |
Aks Engineering & Forestry, Llc *Chris Knight* |
Approved |
6/22/2026 |
|
| 10396 |
Adi Los Expansion |
Corbin Consulting Engineers *Judy Ayala* |
Approved |
6/1/2026 |
|
| 10374 |
Wc 100690 - 205th Road Improvements |
David Evans And Associates *Amanda Blankenship* |
Approved |
6/10/2026 |
|
| 10323 |
Sylvan Culvert Update |
David Evans And Associates, Inc. *Scott * |
Issued |
6/9/2026 |
|